Description HOLD site retained as draft. Conflicting gross/buildable/developable acreage and 300/400 MW planning cases are omitted from structured claims.
Project Details Size (MW) 0
Deal Type Data Center
Site Address 1000 FM 154, Muldoon, TX 78949
Current Zoning Use path unverified
Grid Access No
Utility Fayette Electric Cooperative / TSP route unresolved
Status Listed
Partner Reference BFA-012
Diligence PackageWhat the developer has completed on this site, as declared by the developer.
Not yet available: Fatal flaw analysis, Permit matrix, Interconnection / load study, Utility will-serve / capacity letter, Zoning & entitlement memo, Phase I ESA.
Screening
Fatal flaw analysis Not stated
Interconnection / load study Not stated
Phase I ESA Not stated
Flood zone determination Not stated
Fiber / connectivity study Not stated
Entitlement
Permit matrix Not stated
Utility will-serve / capacity letter Not stated
Zoning & entitlement memo Not stated
Water / sewer will-serve Not stated
Engineering
Wetlands delineation Not stated
Geotechnical report Not stated
Conceptual site plan Not stated
Cost estimate & schedule Not stated
Closing
ALTA / boundary survey Not stated
Title commitment Not stated
Missing something you need before you can move? Ask the developer to scope it — InfraSale can deliver a fatal flaw analysis or permit matrix on request.
Request fatal flaw / permit matrix